02 8024 5922

  • Home
  • Services
  • Projects
  • Contact Us
  • More
    • Home
    • Services
    • Projects
    • Contact Us

02 8024 5922

  • Home
  • Services
  • Projects
  • Contact Us

FOOTINGS REMEDIATION

Foundation Remediation

Foundation Remediation

Foundation Remediation

Padthaway Engineering were engaged on the basis of our capability to complete works in extreme conditions. This project was disaggregated from the broader line project due to the extreme nature of the site in terms of water table, ground conditions, soil type and topography/access. 


Scope of works to remediate all 4 x footings consistent of the client specifications.


Site specific challenges:

  • The tower is located in low lying ground adjacent to a dam wall
  • The site is periodically under water and only accessible during extended periods of low rainfall
  • Ground conditions are wet and soft limiting movement of machines and presenting a constant risk of bogging/sinking of tracked vehicles 
  • Excavations  immediately fill with water requiring constant pumping  
  • Soils are predominantly acid sulfate requiring strict environmental controls 
  • Access via unrated concrete bridge precludes transit/access of heavy equipment 
  • The dam wall presents a steep incline hindering access of men and machines 

Project Execution

Foundation Remediation

Foundation Remediation

Compliance and Pre-Construction:

  • Crew training and PSSR certifications  
  • Environmental, site safety and Covid-19 planning  
  • Project planning and materials sourcing  
  • Construction completed within one working week   


Construction: 

  • Excavation   
  • Existing pier remediation   
  • Steel structure remediation  
  • Formwork and pour Finishing, backfill and compaction   
  • Site remediation

FOOTING CONSTRUCTION

Foundation Construction

Padthaway Engineering were engaged on short notice and on the basis of our capability to complete drilling works in extreme conditions. Padthaway Engineering delivered the works on the eve of the Christmas break inside 1 x working week and with the added complexity of inclement weather and limited line outages 


Site specific challenges:

  • The tower is located atop the Macquarie Pass escarpment in an area of high rainfall 
  • Site entrance from Illawarra Hwy on a blind corner 
  • Ground conditions are wet and soft limiting movement of machines and presenting a constant risk of bogging/sinking of tracked vehicles 
  • Excavations  immediately fill with water requiring constant pumping  
  • Access track was boggy and had an incline, crest and descent 
  • Site required localised Earthworks and pad construction 


Project Execution

Compliance and Pre-Construction: 

  • Crew training and PSSR certifications 
  • Environmental, site safety and Covid-19 planning 
  • Project planning and materials sourcing 
  • Construction completed within one working week 


Construction: 

  • Excavation  
  • Tie in hold-down bolt assembly 
  • Localised Earthworks 
  • Drilling & Cage Placement Finishing, backfill and compaction 
  • Site remediation

FOOTINGS REMEDIATION & ACCESS CLEARING

Footings Remediation

Padthaway Engineering were engaged to complete ~57 tower legs including minor and major remediation's to the new client specifications. Footings remediation's to extend life of towers by ~20 years.


Site specific challenges:

  • Remote locations with treacherous access tracks including erosion, steep inclines and slippery conditions 
  • Large area (Vales Pt to Vineyard) 
  • Ground conditions are wet and soft limiting movement of machines and presenting a constant risk of bogging/sinking of tracked vehicles 
  • High rainfall causing excavations to fill with water requiring constant dewatering 


Project Execution

Compliance and Pre-Construction: 

  • Crew training and PSSR certifications 
  • Environmental, site safety and Covid-19 planning 
  • Project planning and materials sourcing  


Construction: 

  • Excavation 
  • Existing pier remediation  
  • Steel structure remediation 
  • Formwork and pour 
  • Finishing, backfill and compaction 
  • Site remediation

Footings remidiation

ACCESS TRACK REMEDIATION

Padthaway Engineering were commissioned to complete multiple access track remediations. Unprecedented rainfall rendered multiple transmission tower worksites unreachable due to severe ruts, washed out areas and bogs. Existing tracks were first cleared of overgrown vegetation prior to being excavated, boxed and where required Geomesh dropped to prevent further subsidence. New tracks were then constructed to NSW RFS and National Parks and Wildlife Services specifications. Tracks were crowned and cambered with cross banks constructed to manage runoff. Works were competed within the time and budget expectations of the client. 

Challenges

Poor condition of existing tracks

Steep gradient

Biohazard controls required

Waterlogged sites with ongoing runoff impeding works

Landowner requirements/specifications

Padthaway Engineering

02 8024 5922

Copyright © 2023 Padthaway Engineering - All Rights Reserved.

This website uses cookies.

We use cookies to analyse website traffic and optimise your website experience. By accepting our use of cookies, your data will be aggregated with all other user data.

DeclineAccept